Hvammur Hydropower Station

Project details

Project name: Hvammur Hydropower Station

Project location: Þjórsá River, south-west Iceland

Installed capacity: 82 MW

Project owner: Landsvirkjun

 

Assessment details

Assessment tool: Hydropower Sustainability Assessment Protocol (HSAP)

Assessment stage: Preparation

Assessment date: May - November 2012, with an on-site assessment on 21-25 May 2012

No comments were received during the public consultation period.

 

Assessor team for the Hvammur Hydropower Station

 

Sustainability assessment overview

The Hvammur Hydropower Station meets at least basic good practice (a score of 3) for all but one of the 21 assessed topics. The exception is P-1, Communications and Consultations (score of 2), owing to an absence of processes or procedures which would prompt the development of satisfactory grievance mechanisms and communications and consultation plans for all project stages.

 

Results diagram

Previous